Electricity Imports into Singapore: Licensing and Cross-Border Power Deals

An electricity import licence in Singapore is won in stages: a binding proposal to the Energy Market Authority, a Conditional Approval, a Conditional Licence and finally an Electricity Importer Licence. As of October 2026, 13 import projects hold conditional approvals or licences. Success depends on offtake contracts, carbon performance, host-country approvals and financing that line up with EMA's milestones.
Key pointUnder EMA's published submission requirements, contracts signed with a retailer do not count as commercial PPAs; only binding retail contracts with end consumers do. Sponsors who build offtake around retailers may find their proposal weaker than they expected.
At a glance
Staged EMA process
Final Proposal, Conditional Approval, Conditional Licence and then an Electricity Importer Licence, which alone permits construction and commercial operation of the import project.
Pipeline as of 2026
EMA reports Conditional Approvals or Conditional Licences for 13 import projects from Australia, Cambodia, Indonesia, Malaysia and Vietnam, towards an import aim of around 6 GW by 2035.
Carbon ceiling applies
Published requirements prefer zero-emission supply and require an annual emission factor no higher than 0.15 tCO2e/MWh within five years of commercial operations.
Singapore SPV required
The participant must be a Singapore-incorporated company; consortia commonly use a Singapore special purpose vehicle that will eventually hold the importer licence.
Offtake drives bankability
Binding PPAs with Singapore consumers, host-country approvals and committed financing are typically needed before financial close and before the importer licence issues.
Swipe or scroll →
The short answer: how an electricity import licence in Singapore is won
An electricity import licence in Singapore is not a form you file. It is the end point of a staged process run by the Energy Market Authority (EMA): a binding proposal, a Conditional Approval, a Conditional Licence and, only once the conditions are met, an Electricity Importer Licence that allows construction and commercial operation to begin.
As of October 2026, EMA has granted Conditional Approvals and Conditional Licences to 13 import projects drawing on Australia, Cambodia, Indonesia, Malaysia and Vietnam, according to its August 2026 media release. Singapore's stated aim is to import up to around 6 GW of low-carbon electricity by 2035.
For developers, lenders and corporate offtakers, the practical message is that the licence is earned through commercial and financing milestones on both sides of the border. A Conditional Approval signals that EMA finds a proposal attractive; it does not guarantee a licence, a grid connection or a buyer.

What changed in 2025 and 2026
The import programme has moved from announcements to project development, and the questions clients ask about an electricity import licence in Singapore have become correspondingly practical. In May 2025 EMA granted a Conditional Licence to Singa Renewables, a joint venture between TotalEnergies and RGE, for 1 GW of low-carbon electricity from Indonesia; EMA described it as the sixth project to reach that stage, with commercial operations targeted from 2029 (EMA release).
In June 2025 Singapore and Indonesia signed memoranda of understanding covering cross-border electricity trade, carbon capture and storage and a sustainable industrial zone (Ministry of Trade and Industry). In a November 2025 written parliamentary reply, the Government confirmed that since 2023 EMA had issued Conditional Approvals to 11 projects totalling about 8 GW, and that the six Indonesian projects holding Conditional Licences total 3 GW (parliamentary reply).
In August 2026 EMA added Conditional Approvals for 900 MW of solar-plus-storage imports from Johor in Peninsular Malaysia, split between two developers, again with commercial operations targeted around 2029. The same release noted a joint development agreement to study a second interconnection with Peninsular Malaysia.
The Government has also signalled that it will carry out more detailed viability assessments with source-country governments and developers and support the most viable projects. Read together, these statements mean the pipeline is large, but not every approved project should be assumed to reach financial close.
The legal framework behind an electricity import licence in Singapore
The licensing power sits in the Electricity Act 2001, which requires anyone carrying on regulated electricity activities, including importing electricity, to hold a licence unless exempt. EMA administers the Act under the Energy Market Authority of Singapore Act 2001, and it also oversees the Transmission Code and the market rules that govern how imported power is dispatched and settled.
EMA's published submission requirements for electricity import proposals make an important legal point explicit: nothing EMA says or writes during discussions amounts to a Conditional Approval or a licence under the Electricity Act. Rights only arise from the formal instruments, and EMA's statutory powers are preserved throughout.
Three other bodies of law usually matter. First, the host country's electricity, foreign investment, land and export rules decide whether power can leave that country at all. Second, the transit and landing arrangements, including marine cable permits and the Singapore landing site, involve separate approvals. Third, the commercial contracts, from power purchase agreements to construction and financing documents, must align with EMA's licence conditions.
Who can apply
The submission requirements set out a number of "cardinal requirements". The participant must be a Singapore-incorporated company; a consortium may use a Singapore special purpose vehicle. Existing generators face market-share caps, and imports count towards those caps.
Applicants must show credible experience on projects of similar scale and complexity, and the project design must meet minimum import capacity thresholds (0.6 GW for the listed landing sites or 0.3 GW for private landing sites, unless EMA agrees otherwise) and deliver non-intermittent supply within each half-hourly dispatch period. Firms should always check the current version of the document on EMA's website before relying on any threshold.
The process step by step
The staged process for an electricity import licence in Singapore rewards preparation. Each stage narrows the gap between a concept and an operating interconnector, and each one has its own evidential burden.
- Early discussion with EMA. Proposals may be raised with EMA at any time for discussion. This is the moment to test the landing point, the capacity, the carbon profile and the commercial model before anything becomes binding.
- Binding Final Proposal. The participant submits a Final Proposal, which cannot be withdrawn or modified without EMA's approval. It covers the entity, technical design, commercial terms, carbon and financing.
- Proposal bond. Before a Conditional Approval issues, the participant and EMA sign a Proposal Bond Agreement and a bank guarantee is posted, sized by reference to import capacity (S$0.5 million per 100 MWac or part of it, under the published requirements). EMA can call it in specified cases, such as an unapproved withdrawal.
- Conditional Approval. EMA may grant a Conditional Approval to a proposal it considers sufficiently attractive and suitable. Development work, studies and host-country approvals continue.
- Conditional Licence. EMA may issue a Conditional Licence once a project is assessed as technically and commercially viable and at an advanced stage of development. The licence carries obligations and conditions precedent.
- Financial close. Before financial close, developers typically need host-country approvals, signed power purchase agreements with buyers, committed financing and other development milestones, as EMA's 2026 release describes.
- Electricity Importer Licence. When the conditions are satisfied, EMA may issue the Electricity Importer Licence, which allows construction and commercial operations to begin. Ongoing compliance with the Transmission Code and market rules follows.
How EMA evaluates import proposals
EMA's published criteria are qualitative rather than weighted scores. They signal what a winning proposal looks like and where a weak one fails.
| Theme | What EMA looks for | Practical implication |
|---|---|---|
| Ability to supply | On-time delivery, Transmission Code compliance, grid security and reliable supply | Interconnector design, redundancy and the EPC programme are scrutinised early |
| Carbon emissions | Lower expected annual emissions; an emission factor no higher than 0.15 tCO2e/MWh within five years of operation | Fossil-backed firming has limited room; zero-carbon claims need project-generated certificates |
| Competitiveness | Evidence of consumer demand and pricing | Signed, unredacted commercial PPAs with end consumers carry weight |
| Revenue support | Less support, or cheaper, smaller or shorter support, is viewed more favourably | A contract-for-differences or performance contract is possible but not assured |
| Diversity of supply | Avoiding concentration in one source, route or country | A good project can still be deprioritised if it adds concentration risk |
| Robust assumptions | Editable financial model, lifecycle costs and an assumptions book | Optimistic load factors or costs undermine credibility |
EMA also reserves the right to publish participants' identities and to share supply and interconnector locations with other government authorities, so confidentiality strategies should assume that a project's existence will become public once it is approved. Proposal costs are borne by participants whatever the outcome. One detail is easily missed. Under the submission requirements, a "commercial PPA" means a retail contract signed by the participant's retail arm or partner with consumers; contracts signed with a retailer do not count. Quantities not covered by such contracts must be offered through a standing Baseline Offer term sheet.
PPA and offtake structures for imported power
Offtake is where most import projects succeed or stall, and it is often the deciding factor in whether an electricity import licence in Singapore is ultimately issued. The core instrument is a long-term power purchase agreement with Singapore consumers, usually large industrial users, data-centre operators or other energy-intensive businesses. Our page on renewable energy contracts in Singapore covers the drafting mechanics in more detail.
Buyers typically care about price indexation, curtailment and outage allocation, the treatment of renewable energy certificates, change-in-law risk across two jurisdictions and what happens if the interconnector is delayed. Developers care about bankability, which means tenor, creditworthiness of the buyer and termination payments.
Where a developer asks EMA for revenue support, the published framework contemplates either a two-way contract-for-differences or a performance contract (not both), with tenors of up to 25 years and 15 years as the base option. Support is discretionary and can be reduced for underperformance, so it should be modelled as upside rather than assumed. For corporate buyers comparing import PPAs with domestic options, our article on energy PPAs and market permissions sets out the domestic baseline.
Build the PPA around the licence stages. Conditions precedent should track EMA milestones (Conditional Licence, Importer Licence, commercial operation), long-stop dates should reflect realistic cable and host-country timelines, and termination rights should be clear if EMA does not issue the licence. A PPA that assumes a fixed start date with no regulatory long-stop is a common source of later disputes.
Illustrative scenario: a solar-plus-storage import consortium
This scenario is illustrative only; the parties are generic and it does not describe any real project.
A regional developer and an international utility form a Singapore SPV to import firmed solar power from a neighbouring country. The SPV secures a Conditional Approval after posting the proposal bond. Its plan relies on signing PPAs with two data-centre operators and securing host-country export approval within 18 months.
Twelve months in, one buyer insists on a price reopener tied to grid tariffs, and the host-country approval is delayed by a change in local regulation. The SPV's lenders will not commit until both are resolved. Because the consortium agreement had no mechanism for funding extended development costs, the partners disagree on who bears them.
The lessons for anyone pursuing an electricity import licence in Singapore are familiar from project finance in Singapore: align the consortium agreement, PPAs and financing conditions with the EMA stages from day one; allocate development-cost overruns expressly; and keep a dispute resolution clause, usually Singapore-seated arbitration, that works across both jurisdictions.
Risks and common mistakes
Treating a Conditional Approval as a licence
A Conditional Approval is an in-principle signal. It does not authorise construction or commercial operation and it can lapse if milestones are missed. Investment memos, lender presentations and offtake marketing should describe it accurately; overstating the status can create misrepresentation risk with buyers and co-investors.
Track every condition in the approval and the subsequent Conditional Licence, with an owner and a date for each.
Underestimating host-country risk
The Singapore licence is only half the story. Export permissions, land rights, local-content rules, grid access and foreign ownership limits in the source country can each delay or stop a project. Changes in host-country policy are a recurring risk that Singapore's process cannot cure.
Map host-country approvals at the same level of detail as the EMA process, and consider stabilisation or change-in-law protections where they are available.
Carbon and certificate assumptions that do not hold
EMA's published requirements prefer zero-emission supply and set a ceiling on the annual emission factor after the first years of operation. Zero-carbon status can be claimed through sufficient certificates generated by the import project itself; certificates from other sources are not accepted.
Projects that depend on gas firming or purchased certificates should test their carbon trajectory carefully before submitting a binding proposal.
Weak consortium and SPV documentation
Many import projects are consortia of developers, utilities and financial investors. Gaps in decision-making, funding obligations, exit rights and deadlock resolution tend to surface exactly when a Conditional Licence condition is at risk.
A robust shareholders' agreement, reviewed alongside the licence conditions, reduces that risk. Our page on joint ventures and strategic alliances covers the main protections.
Overlooking the market-share cap and change of ownership
Imports count towards the market-share caps that apply to existing generators. An incumbent generator joining an import consortium should model the cap before committing. Equally, transferring interests in the SPV after approval may require EMA's consent under the licence conditions, which affects exit planning for financial investors.
Cross-border angle: contracts, disputes and investment protection
Every project behind an electricity import licence in Singapore is cross-border by design, and the contract set usually spans at least two legal systems. Singapore law commonly governs the PPAs and the SPV documents, while host-country law governs land, generation permits and local construction contracts. EMA's own proposal process is governed by Singapore law with Singapore court jurisdiction.
Investors should consider whether a bilateral or regional investment treaty protects their investment in the host country; our page on investor-state arbitration explains how treaty structuring works. For commercial disputes, international arbitration in Singapore remains the default choice for most regional energy contracts.
TRW & Co's network across Singapore, Bangladesh, the UK, the UAE and China is useful where sponsors, lenders or equipment suppliers sit in different jurisdictions. Where Singapore court or tribunal representation is required, we work alongside Singapore-qualified counsel; host-country advice is coordinated with local counsel.
What to do next: a checklist for sponsors and buyers
Whether you are a developer seeking an electricity import licence in Singapore or a corporate buyer considering imported power, these steps reduce regulatory and commercial risk:
- Read EMA's current submission requirements in full and record which cardinal requirements apply to your project.
- Confirm the landing option (listed or private) and the minimum capacity that applies to it.
- Model the emission factor trajectory and certificate strategy against EMA's ceiling before committing to a binding Final Proposal.
- Line up signed, unredacted commercial PPAs with end consumers, not retailers, and plan the Baseline Offer for any merchant quantities.
- Arrange the proposal bond and confirm who in the consortium bears it if it is called.
- Map host-country export, land and investment approvals with local counsel and build long-stop dates around them.
- Align the consortium agreement, PPA conditions precedent and financing conditions with the Conditional Licence milestones.
- Take early advice on the structure of the energy project in Singapore as a whole, including landing infrastructure and permits.
The route to an electricity import licence in Singapore is long but predictable for teams that respect its stages. If you are preparing a proposal, negotiating an import PPA or investing in an import consortium, contact TRW & Co to discuss the regulatory and contractual roadmap.
Frequently asked questions
01Who grants an electricity import licence in Singapore?
The Energy Market Authority grants licences under the Electricity Act 2001. Importers move through a staged process: a binding Final Proposal, a Conditional Approval, a Conditional Licence and finally an Electricity Importer Licence. EMA has stated that nothing said in discussions amounts to an approval or licence; only the formal instruments create rights. Projects must also obtain separate approvals in the source country and for transmission and landing infrastructure, so the Singapore licence is one part of a wider permitting picture.
02What is the difference between a Conditional Approval and a Conditional Licence?
A Conditional Approval is granted to a Final Proposal that EMA considers sufficiently attractive and suitable, after the participant signs a proposal bond agreement. A Conditional Licence comes later, when EMA assesses the project as technically and commercially viable and at an advanced stage of development. The Conditional Licence carries obligations that must be met before EMA may issue the full Electricity Importer Licence, which permits construction and commercial operations.
03How much electricity does Singapore plan to import?
Singapore aims to import up to around 6 GW of low-carbon electricity by 2035, as EMA has restated in its media releases. By August 2026, EMA had granted Conditional Approvals and Conditional Licences to 13 projects from Australia, Cambodia, Indonesia, Malaysia and Vietnam. The Government has said it will carry out more detailed viability assessments with source countries and developers, so not every approved project should be assumed to proceed.
04Can a foreign company apply directly to import electricity?
Under EMA's published submission requirements, the participant must be a Singapore-incorporated company. Foreign developers and utilities therefore usually form a Singapore special purpose vehicle, often as a consortium, to submit the proposal and hold any licence. The SPV's constitution and shareholders' agreement should anticipate EMA's licence conditions, including consent requirements for changes in ownership, funding obligations and what happens if a licence condition cannot be met.
05Do import projects need signed PPAs before applying?
Evidence of consumer demand is one of EMA's evaluation themes, and signed, unredacted PPAs with end consumers carry weight. Contracts with retailers do not count as commercial PPAs under the published requirements. Quantities not contracted must be offered through a standing Baseline Offer term sheet. In practice, binding PPAs with buyers are also among the milestones that developers need before reaching financial close, so offtake strategy should start early.
06Does EMA provide revenue support to electricity importers?
EMA may offer revenue support on request, in the form of either a two-way contract-for-differences or a performance contract, but not both. The published framework contemplates tenors of up to 25 years, with 15 years as the base option. Support is discretionary, proposals needing less support are viewed more favourably, and EMA may reduce support for underperformance. Sponsors should therefore treat support as a possible enhancement rather than a foundation of the business case.
Sources and official materials
- EMA grants Conditional Approvals for 900 MW electricity trade between Peninsular Malaysia and Singapore — August 2026 approvals, 13-project pipeline and pre-financial-close milestones
- Singapore grants Conditional Licence to Singa Renewables for electricity imports from Indonesia — Conditional Licence stage, path to Electricity Importer Licence and 6 GW aim
- EMA Electricity Imports: Submission Requirements — Cardinal requirements, evaluation themes, proposal bond, carbon and revenue support
- Written reply to PQ on regional importers given Conditional Approvals or Licences by EMA — November 2025 update on 11 approved projects and viability assessments
- Singapore and Indonesia sign three MOUs on cross-border electricity trade, CCS and a sustainable industrial zone — June 2025 bilateral framework for electricity trade
- Electricity Act 2001 (Singapore Statutes Online) — Statutory licensing framework administered by EMA